What the trial does not do

Describes RotoScheduler 0.2.1 · checked 2026-09-14 D5

Read this before assessing a real production plan with the trial.

  • The sample is a worked example for learning the board. Replace its assumptions with measured factory data before assessing a real plan.
  • Parts planned are not parts produced. The trial does not record live machine output or reconcile the plan with actual production.
  • Heating and cooling targets alone do not establish acceptable process limits. Read Projected, process windows unknown and closing-time warnings as unresolved timing checks.
  • The phase view describes fixed-turret machines. It does not schedule independent arms competing for an oven or a cooler.
  • The arm-layout viewing pane is hidden in this trial. Use the board and its timing inspector.
  • 0.2 has manual assignment, movement, unscheduling, and undo and redo. Pins and freezes, extending production by resizing a run, bulk moves, copying a mounting, and editing availability on the board are not included.
  • Factory and job data are entered through Factory inputs on the desktop. A general spreadsheet importer and a connection to a customer's order or shop-floor system are not included.
  • Keep a named version before an experiment and a saved .json copy for work you need to keep or share.

Where your plant works differently from what the app assumes, the comment button under every page reaches us.

Comments and questions

The app's rules are our reading of the physics; where your plant knows better, the app changes.